AIA A201 General Conditions: What Every ARE Candidate Must Know

A focused overview of AIA A201-2017 - the general conditions document that defines owner, contractor, and architect roles during construction - tested across PcM, PjM, and CE divisions.

August 7, 2025

The A201 Is Not Just a CE Document

Many candidates treat AIA A201 as a Construction Evaluation topic only. That is a mistake. The A201 General Conditions of the Contract for Construction defines the roles, authorities, and responsibilities of all three parties - Owner, Contractor, and Architect - and it is tested on PcM, PjM, and CE. Understanding its 15 articles is critical across at least three of the six ARE divisions.

The A201 is a companion to the owner-contractor agreement (AIA A101 for stipulated sum, A102 for GMP). It is incorporated by reference into the construction contract and governs the project from Notice to Proceed through Final Completion. It is not signed on its own - it is incorporated into the owner-contractor agreement.

The 15 Articles at a Glance

ArticleTopicWhy It Matters for the ARE
1General ProvisionsDefines key terms; establishes contract document hierarchy
2OwnerOwner obligations, right to carry out work, stop-work rights
3ContractorContractor's general responsibility, supervision, means and methods
4ArchitectArchitect's authority and limitations during construction
5SubcontractorsSubcontractor approval, substitution, assignment
6Separate ContractorsOwner's right to use separate contractors on the same site
7Changes in the WorkChange Orders, CCDs, ASIs - heavily tested
8TimeContract time, delays, time extensions
9Payments and CompletionSchedule of values, pay apps, retainage, substantial completion
10Protection of PersonsSafety, hazardous materials
11Insurance and BondsContractor's required insurance, owner's property insurance
12Uncovering and CorrectionDefective work, one-year correction period
13Miscellaneous ProvisionsGoverning law, successors, written notices
14Termination or SuspensionConditions and procedures for each party's termination rights
15Claims and DisputesInitial decision maker (IDM), mediation, arbitration

Articles Most Tested on the ARE

Article 4: The Architect's Authority

The architect acts as the Initial Decision Maker (IDM) for claims unless a different IDM is named. The architect has authority to reject work that does not conform to the contract documents, approve submittals, and certify payment. Critically, the architect does not control the contractor's means and methods - this is a common exam trap.

Article 7: Changes in the Work

Three mechanisms for changing the work: Change Orders (bilateral, require agreement on cost and time), Construction Change Directives or CCDs (unilateral, owner-directed when agreement cannot be reached), and Architect's Supplemental Instructions or ASIs (minor changes that do not affect cost or time). Know which tool applies in which situation.

Article 9: Payments and Completion

Contractor submits a schedule of values before the first pay application. The architect reviews pay applications and, if they conform, issues a Certificate for Payment within 7 days. The owner must pay within 7 days of certificate issuance. Retainage (typically 10%) is held until substantial completion.

The Architect's Role vs. Limitations

  • Can: Reject work, certify payment, interpret contract documents, issue ASIs, and act as IDM.
  • Cannot: Direct the contractor's means and methods, supervise safety, or take actions that would make the architect liable for construction operations.

Start Studying on AREprep

AREprep covers all six ARE 5.0 divisions with flashcards and practice exams built around the actual NCARB exam guides - so every hour you study is targeted at what the exam actually tests.