Back to Blog
Division Guides7 min read

Project Closeout in Architecture: The Complete Checklist for ARE Candidates

Every step in the architectural project closeout process - substantial completion, punch list, final completion, and required documents - organized as a testable checklist for the ARE PjM and CE exams.

September 3, 2025

Project Closeout Is More Than Handing Over the Keys

Project closeout is the final phase of construction administration - and one of the most procedurally complex. The steps from contractor's notice of substantial completion through final payment involve multiple formal certifications, documentation requirements, and contractual obligations. The ARE tests closeout knowledge across both PjM and CE, expecting candidates to know the sequence of closeout events, the documents involved, and the legal significance of each step.

The Closeout Sequence

Step 1: Contractor's Notice of Substantial Completion

The contractor notifies the architect that the work is substantially complete and requests an inspection. The architect and owner conduct a walkthrough to verify. If the architect agrees, the AIA G704 Certificate of Substantial Completion is issued. If not, the architect informs the contractor of deficiencies that must be corrected before substantial completion can be certified.

Step 2: Certificate of Substantial Completion (AIA G704)

Substantial completion is the point at which the work is sufficiently complete in accordance with the contract documents that the owner can occupy or utilize the work for its intended purpose. The G704 establishes the date of substantial completion, which triggers several contractual events: the one-year correction period begins, retainage reduction often occurs, the owner assumes responsibility for insurance and utilities, and the deadline for filing mechanics liens begins to run in many states.

Step 3: Punch List

The punch list (or deficiency list) is a list of incomplete or deficient work items identified during the substantial completion inspection. The contractor must complete all punch list items for the work to reach final completion. The architect monitors punch list completion and should not certify final completion until all items are resolved. Under AIA A201, the architect should not include on the punch list items that would normally be part of the contractor's ongoing Work - the punch list addresses deficiencies, not routine completion.

Step 4: Contractor Submits Final Application for Payment

After all punch list items are complete and the work reaches final completion, the contractor submits the final Application and Certificate for Payment (AIA G702/G703), accompanied by the required closeout documents.

Step 5: Required Closeout Submittals

  • Final record drawings (as-built drawings) marked to show field conditions
  • Operations and maintenance manuals for all systems and equipment
  • Warranties from contractors and manufacturers
  • Certificates of occupancy from the building official
  • Contractor's Affidavit of Payment of Debts and Claims (AIA G706)
  • Contractor's Affidavit of Release of Liens (AIA G706A)
  • Consent of Surety to Final Payment (AIA G707) if a payment bond was provided
  • Keys, access codes, and attic stock (extra material for future repairs)

Step 6: Architect Certifies Final Payment

The architect reviews the final application and closeout submittals. If all requirements are met, the architect issues a Certificate for Payment for the final amount - which typically includes the retained funds. Final payment releases the contractor from most contractual obligations except the one-year correction period warranty.

The One-Year Correction Period

Under AIA A201 Article 12, the contractor is required to correct defective work discovered within one year after the date of substantial completion, at no cost to the owner. This is not the same as a warranty - it is a contractual obligation. Manufacturers' warranties may be longer (e.g., roofing warranties of 10–20 years) and are transferred to the owner as part of closeout.

Key Exam Points

  • G704 = Certificate of Substantial Completion - triggers one-year correction period.
  • G706 = Contractor's Affidavit of Payment of Debts; G706A = Release of Liens.
  • G707 = Consent of Surety to Final Payment.
  • Certificate of Occupancy is issued by the building official, not the architect.
  • Substantial completion vs. final completion: SC = work usable; FC = all work complete.

Study PjM on AREprep

AREprep’s PjM flashcards cover every concept on this exam with spaced repetition, and the practice exams mirror the real question formats so the actual test feels familiar.

Ready to put this into practice?

AREprep has 400 original flashcards, 30 timed mini exams, and 3 full-length simulations for every ARE division.