Why CE Tests Procedural Knowledge
Construction & Evaluation is the most procedural ARE division. It tests your understanding of construction administration - not design or technical systems, but the processes that govern how a project gets built. Candidates with limited CA experience often struggle because they haven't lived through these procedures.
Mistake #1: Confusing the Change Order Process
The change process under AIA A201 follows a specific sequence:
- Proposed Change: Owner or architect identifies a change.
- Construction Change Directive (CCD): Owner directs work to proceed before price is agreed upon. Only the owner and architect sign.
- Change Order (CO): Formal agreement on scope, cost, and time. Signed by owner, architect, AND contractor.
The most common mistake is thinking a CCD requires the contractor's signature. It does not - that's the whole point. A CCD allows work to proceed while cost is negotiated.
Read the full construction administration deep dive
Mistake #2: Misunderstanding the Architect's CA Role
Under AIA A201, the architect:
- Does review submittals for general conformance with design intent.
- Does visit the site at intervals appropriate to the stage of construction.
- Does serve as the Initial Decision Maker (IDM) for claims.
- Does NOT supervise construction means, methods, or safety.
- Does NOT guarantee the contractor's work.
- Does NOT have authority to stop the work (only the owner can do that).
Mistake #3: Pay Application Errors
The Schedule of Values and pay application process are frequently tested:
- The contractor submits a Schedule of Values before the first pay application.
- The architect reviews and certifies the pay application - the architect does NOT approve it (the owner approves payment).
- Retainage is typically 5-10% withheld from each payment. It is released at substantial completion (sometimes partial release) or final completion.
See the construction admin cheat sheet
Mistake #4: Confusing Substantial vs. Final Completion
- Substantial completion: The project is sufficiently complete that the owner can use it for its intended purpose. The architect issues a Certificate of Substantial Completion. Warranty periods typically begin at this point.
- Final completion: All punch list items are resolved, all documentation is submitted, and all contractual obligations are fulfilled. The architect issues a final Certificate for Payment.
Mistake #5: Submittal Review Confusion
The architect reviews submittals for general conformance with the design intent. Common stamp options:
- No Exceptions Taken: Approved as submitted.
- Make Corrections Noted: Minor changes required, resubmission not needed.
- Revise and Resubmit: Significant changes needed, must resubmit.
- Rejected: Does not conform to contract documents.
How to Avoid These Mistakes
- Study the AIA A201 General Conditions thoroughly - most CE questions reference it.
- Practice with CE mini exams to test your procedural knowledge.
- Review CE flashcards on CA terminology.
- Read the CE glossary for precise definitions of CA terms.