Common ARE CE Mistakes - What Trips Up Most Candidates

Avoid these common mistakes on the ARE 5.0 Construction & Evaluation exam. CA procedures, change orders, and closeout pitfalls.

Why CE Tests Procedural Knowledge

Construction & Evaluation is the most procedural ARE division. It tests your understanding of construction administration - not design or technical systems, but the processes that govern how a project gets built. Candidates with limited CA experience often struggle because they haven't lived through these procedures.

Mistake #1: Confusing the Change Order Process

The change process under AIA A201 follows a specific sequence:

  1. Proposed Change: Owner or architect identifies a change.
  2. Construction Change Directive (CCD): Owner directs work to proceed before price is agreed upon. Only the owner and architect sign.
  3. Change Order (CO): Formal agreement on scope, cost, and time. Signed by owner, architect, AND contractor.

The most common mistake is thinking a CCD requires the contractor's signature. It does not - that's the whole point. A CCD allows work to proceed while cost is negotiated.

Read the full construction administration deep dive

Mistake #2: Misunderstanding the Architect's CA Role

Under AIA A201, the architect:

  • Does review submittals for general conformance with design intent.
  • Does visit the site at intervals appropriate to the stage of construction.
  • Does serve as the Initial Decision Maker (IDM) for claims.
  • Does NOT supervise construction means, methods, or safety.
  • Does NOT guarantee the contractor's work.
  • Does NOT have authority to stop the work (only the owner can do that).

Mistake #3: Pay Application Errors

The Schedule of Values and pay application process are frequently tested:

  • The contractor submits a Schedule of Values before the first pay application.
  • The architect reviews and certifies the pay application - the architect does NOT approve it (the owner approves payment).
  • Retainage is typically 5-10% withheld from each payment. It is released at substantial completion (sometimes partial release) or final completion.

See the construction admin cheat sheet

Mistake #4: Confusing Substantial vs. Final Completion

  • Substantial completion: The project is sufficiently complete that the owner can use it for its intended purpose. The architect issues a Certificate of Substantial Completion. Warranty periods typically begin at this point.
  • Final completion: All punch list items are resolved, all documentation is submitted, and all contractual obligations are fulfilled. The architect issues a final Certificate for Payment.

Mistake #5: Submittal Review Confusion

The architect reviews submittals for general conformance with the design intent. Common stamp options:

  • No Exceptions Taken: Approved as submitted.
  • Make Corrections Noted: Minor changes required, resubmission not needed.
  • Revise and Resubmit: Significant changes needed, must resubmit.
  • Rejected: Does not conform to contract documents.

How to Avoid These Mistakes

  • Study the AIA A201 General Conditions thoroughly - most CE questions reference it.
  • Practice with CE mini exams to test your procedural knowledge.
  • Review CE flashcards on CA terminology.
  • Read the CE glossary for precise definitions of CA terms.

Keep Studying

Sign up free to access flashcards and practice exams for Construction & Evaluation.

Ready to put this into practice?

AREprep has 400 flashcards, 30 mini exams, and 3 full-length simulations for CE.