Cheat SheetCE

ARE Construction Administration Cheat Sheet

CA timeline, submittal process, RFI workflow, change order procedure, pay applications, and completion milestones for the ARE 5.0 exam.

Construction Administration Quick Reference

This cheat sheet covers the CA phase procedures tested heavily on the ARE 5.0 CE exam. See the Construction Administration topic guide for full details.

CA Phase Timeline

PhaseKey ActivitiesWho
Pre-constructionPre-construction meeting, submittal schedule, schedule of valuesContractor, Architect, Owner
ConstructionSubmittals, RFIs, site visits, pay apps, change ordersAll parties
Substantial completionPunch list, certificate of substantial completionArchitect certifies
Final completionAll punch list items resolved, final payment, warranties beginArchitect certifies
Post-constructionWarranty period, 11-month walkthroughArchitect (if contracted)

Submittal Process

StepActionResponsible Party
1Contractor prepares submittal scheduleContractor
2Contractor reviews submittals for contract complianceContractor
3Contractor transmits to architect with stamp of approvalContractor
4Architect reviews for design intent onlyArchitect
5Architect returns with action stampArchitect
6Contractor distributes to subcontractors/suppliersContractor

Architect action stamps:

  • Approved / No Exceptions Taken: Proceed with fabrication
  • Approved as Noted: Proceed with noted corrections
  • Revise and Resubmit: Correct and resubmit before fabrication
  • Rejected: Non-compliant; resubmit with conforming product

Key point: Architect reviews for design intent and general conformance only. Architect does NOT approve means, methods, or contractor's responsibility for dimensions and quantities.

RFI (Request for Information) Workflow

StepActionTimeline
1Contractor identifies question/conflictAs discovered
2Contractor submits RFI to architectIn writing
3Architect reviews and respondsPer contract (typically 7–10 business days)
4If design change results, may require ASI or change orderVaries
5Architect logs all RFIs with number, date, statusOngoing

Change Order Procedure

DocumentDescriptionAuthorization
Architect's Supplemental Instruction (ASI)Minor clarifications, no cost/time changeArchitect issues
Proposal Request (PR)Architect requests contractor price for potential changeArchitect issues
Change Order Proposal (COP)Contractor prices the proposed changeContractor submits
Construction Change Directive (CCD)Owner directs work before agreement on cost/timeOwner + Architect sign
Change Order (CO)Formal agreement on scope, cost, and time changesOwner + Contractor + Architect sign

Pay Application Process (AIA G702/G703)

StepAction
1Contractor submits Application for Payment with Schedule of Values
2Architect reviews work in place vs. amounts claimed
3Architect issues Certificate for Payment (approves amount)
4Owner makes payment (minus retainage, typically 5–10%)
5Retainage released after substantial or final completion

Key AIA documents: G702 = Application and Certificate for Payment. G703 = Continuation Sheet (Schedule of Values breakdown).

Substantial vs Final Completion

MilestoneDefinitionConsequences
Substantial completionWork sufficiently complete for owner to occupy/use for intended purposeWarranties begin; owner assumes risk of loss; punch list created; retainage may be partially released
Final completionAll work complete including punch list itemsFinal payment due; all retainage released; contractor’s obligations fulfilled except warranties

Warranty Periods

  • General contractor warranty: 1 year from substantial completion (per AIA A201)
  • Roofing: 10–20 year manufacturer warranty (2-year contractor workmanship typical)
  • Structural: 10-year statute of repose in many jurisdictions
  • MEP equipment: Varies; manufacturer warranty + contractor installation warranty
  • 11-month walkthrough: Architect inspects before 1-year warranty expires

Study CA procedures with CE flashcards and CE mini exams. Sign up free to track your progress.