Cheat SheetPDD

ARE Specifications Cheat Sheet

CSI MasterFormat divisions, specification types, SectionFormat parts, and coordination between drawings and specs for the ARE 5.0 exam.

Specifications Quick Reference

This cheat sheet covers CSI specifications format and content tested on the ARE 5.0 PDD and CE divisions. See the Specifications & CSI topic guide for comprehensive study.

CSI MasterFormat Divisions

DivisionTitleExamples
00Procurement and Contracting RequirementsBidding documents, contracts, bonds (NOT specifications)
01General RequirementsSummary, price/payment procedures, submittals, quality requirements, temporary facilities
02Existing ConditionsDemolition, site assessment, hazmat abatement
03ConcreteCast-in-place, precast, reinforcing
04MasonryUnit masonry, stone, glass block
05MetalsStructural steel, metal joists, metal decking, miscellaneous metals
06Wood, Plastics, CompositesRough carpentry, finish carpentry, millwork, structural plastics
07Thermal and Moisture ProtectionInsulation, waterproofing, roofing, sealants, fireproofing
08OpeningsDoors, windows, hardware, glazing, skylights
09FinishesPlaster, gypsum board, tile, flooring, painting
10SpecialtiesSignage, lockers, toilet partitions, fire extinguishers
11EquipmentKitchen equipment, athletic equipment, lab equipment
12FurnishingsFurniture, window treatments, casework
13Special ConstructionPre-engineered structures, pools, clean rooms
14Conveying EquipmentElevators, escalators, dumbwaiters
21Fire SuppressionSprinkler systems, standpipes
22PlumbingPiping, fixtures, domestic water, sanitary waste
23HVACDuctwork, air handling, chillers, boilers
25Integrated AutomationBuilding automation systems (BAS)
26ElectricalWiring, lighting, power distribution, generators
27CommunicationsData, voice, audio-visual systems
28Electronic Safety and SecurityFire alarm, access control, surveillance
31EarthworkGrading, excavation, fill
32Exterior ImprovementsPaving, landscaping, fencing, irrigation
33UtilitiesWater, sewer, storm drainage, gas

Key note: Division 00 is procurement, NOT specifications. Division 01 is administrative/procedural. Divisions 02–49 are technical specifications.

SectionFormat (3-Part Spec Section)

PartTitleContent
Part 1GeneralReferences, submittals, quality assurance, delivery/storage, warranty, system description
Part 2ProductsMaterials, manufacturers, fabrication, finishes, source quality control
Part 3ExecutionPreparation, installation, field quality control, cleaning, protection, schedules

Specification Types

TypeDescriptionWhen to UseRisk
Prescriptive (descriptive)Describes physical/chemical properties and methodsWhen exact properties are known and criticalSpecifier assumes performance risk
PerformanceStates required results/outcomes, not how to achieveWhen outcome matters more than methodContractor assumes performance risk
Proprietary (brand name)Names specific manufacturers and model numbersWhen only one product is acceptableLimits competition; may increase cost
Reference standardCites published standards (ASTM, ANSI, UL)When industry standards define requirementsMust verify standard is current edition

"Or equal" clause: Allows substitution of products meeting same performance criteria. Architect reviews and approves substitutions.

Project Manual Organization

SectionContents
Bidding requirementsAdvertisement/invitation to bid, instructions to bidders, bid forms
Contracting requirementsAgreement, bonds, certificates, conditions (general + supplementary)
SpecificationsDivision 01–49 technical sections

Project manual vs construction documents: Project manual = specifications + procurement/contracting. Construction documents = drawings + specifications. Drawings show location, size, and relationship. Specifications describe quality, standards, and methods.

Drawings vs Specifications Coordination

Drawings ShowSpecifications Describe
Location and arrangementQuality of materials
Dimensions and sizesStandards and test methods
Spatial relationshipsInstallation procedures
Quantities (by implication)Manufacturer requirements
Configuration and detailsWorkmanship standards

Conflict rule (AIA A201 §1.2.1): In case of conflict between drawings and specifications, the architect interprets. Neither takes automatic precedence (unlike older conventions).

Key Specification Concepts

  • Closed spec: Names specific product(s) only; no substitutions
  • Open spec: Allows substitutions that meet performance criteria
  • Base bid spec: Names one product as standard with "or approved equal"
  • Addenda: Changes to bidding documents issued BEFORE bid opening
  • Modifications: Changes AFTER contract execution (change orders, ASIs)
  • Supplementary conditions: Modify or supplement AIA A201 General Conditions for project-specific requirements

Study specifications with PDD flashcards and CE flashcards. Sign up free to track your progress.